(1) Interface Energy Meters shall be installed and maintained by the State Transmission Utility for open access in transmission 1 [and ] by the distribution licensee for open access in distribution at the cost of the open access customers.
1 Subs. for “HPERC (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2007”, vide Not. No. HPERC/ 418 dated 7 th December, 2012, published in the R H.P. dated 10 th December, 2012 at p.5409-5415.
2 The words “as estimated by the State Load Despatch Centre and applied” omitted vide Not. No.
HPERC/ 418 dated 7 th December 2012 , published in the R.H.P. dated 10 th December 2012 at p. 5409-5415.
3 Ins. vide Not. No. HPERC/ 418 dated 7 th December 2012, published in the R H.P. dated 10 th December 2012 at p. 5409-5415.
Compendium of HPERC Regulations, March 2021 17
(2) Interface Energy Meters installed shall be in accordance with Annexure-2 to the Grid Code.
(3) Interface Energy Meters for the open access customer shall be open for inspection by any person authorized by the State Transmission Utility/ Distribution Licensee or the State Load Despatch Centre.