Section 33: Normative Capital cost

The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions…State Regulations of Himachal Pradesh · 2003

(1) In case of SHPs, the normative capital cost inclusive of 28 Compendium of HPERC Regulations, March 2021 all its components as specified in regulation 20 of these Regulations, for the control period shall be as under:- S.No. Category of small hydro project Rupees in Lac per MW

(i) Above 100 kW to 2 MW capacity 780

(ii) Above 2 MW to 5 MW capacity 750

(iii) Above 5 MW to 25 MW capacity 700

(2) The subsidy/grant/budgetary support or incentives provided by the Central/State Government shall be adjusted in accordance with the regulation 21 of these Regulations.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012
Section33
Marginal noteNormative Capital cost
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.