Section 34: Normative saleable energy

The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions…State Regulations of Himachal Pradesh · 2003

(1) The normative saleable energy at the interconnection point for the purpose of generic levellised tariff shall be computed on the following lines namely :-

(i) the normative annual capacity utilisation factor (CUF) for all the SHPs upto 25 MW shall be 55%;

(ii) the normative annual energy worked out at the normative CUF under preceding clause (i) for the installed capacity shall be adjusted for the auxiliary consumption, transformation losses and the losses in the project line(s) at the normative rates as per regulations 36 and 37;

(iii) the energy worked out under preceding clause (ii) shall be further reduced by the permissible rate of the free power subject to a maximum of 13%, for any year or part thereof, consistent with the National Hydro Policy, Tariff Policy and the policy of the State Government for allotment of sites of SHPs in the manner as laid down in regulation 35, so as to arrive at the yearwise normative net saleable energy at the interconnection point which shall be taken into account for working out the generic levellised tariff.

(2) The normative capacity utilization factor (CUF) under clause (i) of sub-regulation (1) takes into account the impact of mandatory release of water discharge immediately downstream of diversion structure of the project based on the existing instructions of the State Government which provide that for the purpose of determination of minimum discharge, the threshold value not less than 15% of the minimum inflow observed in the lean season shall be considered.

(3) The normative year wise net saleable energy for the purpose of project specific tariff determination shall also be worked out on similar lines given in sub-regulations (1) and (2) but by taking into account the annual Capacity Utilisation Factor (CUF) in accordance with clause (ii) of sub-regulation (1) of regulation 14, the normative auxiliary consumption and transformation losses under regulation 36 and the energy losses in the project line under regulation 37.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012
Section34
Marginal noteNormative saleable energy
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.