Section 37: Energy losses

The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions…State Regulations of Himachal Pradesh · 2003

(1) The normative energy losses in the project line(s) shall be 0.7% of the net generation (i.e. after deducting auxiliary consumption and transformation losses, on normative basis, from the gross generation).

(2) For the project specific levellised tariff, the percentage losses worked out on the basis of actual length of the project line(s), conductor size and expected power flow shall be taken into consideration.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) Regulations, 2012
Section37
Marginal noteEnergy losses
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.