The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions…State Regulations of Himachal Pradesh · 2003
(1) The normative energy losses in the project line(s) shall be 0.7% of the net generation (i.e. after deducting auxiliary consumption and transformation losses, on normative basis, from the gross generation).
(2) For the project specific levellised tariff, the percentage losses worked out on the basis of actual length of the project line(s), conductor size and expected power flow shall be taken into consideration.
Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.