The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012State Regulations of Himachal Pradesh · 2003
(1) Notwithstanding anything contained in any other law for the time being in force, all the works erected for providing supply in pursuance of requisition by the applicant, or any portion thereof, which may have been paid for by the applicant making requisition, shall be maintained by the licensee and the licensee shall also have the right to supply electricity to any other prospective applicants or the consumers, through the said works and the said works shall become the property of the licensee.
(2) The interface point of commencement of supply, as determined under the provisions of the Supply Code and the relevant agreements, shall constitute the liability between the licensee and the consumer/ applicant.
Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Suppl… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.