Section 16: Accounting of the amounts recovered

The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012State Regulations of Himachal Pradesh · 2003

The amounts recovered by the distribution licensee under various provisions of these Regulations on various accounts for supply at different voltage levels shall be accounted for separately as capital receipts under separate accounting heads and sub-heads for permanent and temporary connections and also each type of charges as well as for each category of voltage level and shall, subject to the provisions of sub-regulations (5), (6), (7) and (8) of regulation 5, be used exclusively for meeting a part of the capital expenditure under the capital expenditure plan:

16 Compendium of HPERC Regulations, March 2020

Provided that such capital receipts shall, as far as possible, be utilized in an equitable proportion of the estimated cost of various works of the respective categories and respective voltage levels:

Provided further that the capital receipts in respect of the works required exclusively for an applicant or group of applicants shall be used for such exclusive works only.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012
Section16
Marginal noteAccounting of the amounts recovered
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Suppl… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.