Section 17: Execution of works

The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012State Regulations of Himachal Pradesh · 2003

The service lines and other works required for supplying power to the applicant(s) shall normally be executed by the distribution licensee:

Provided that the applicant or the consumer, as the case may be, may, with the prior approval of the distribution licensee which shall ordinarily not be refused, execute the service line through an electrical contractor licensed by the Electrical Inspector, and in such cases, the following provisions shall apply-

(i) all the requisite clearances under various laws shall be obtained by the applicant;

(ii) the applicant shall be liable to pay the departmental charges @ 6.25% of the estimated cost for the specific works or of the corresponding amount worked out by accounting for the average/normative rates, if approved by the Commission under regulation 4, whichever is higher;

(iii) such option shall be available to the applicant only for the service line to be executed exclusively for the applicant; and

(iv) works other than service line shall be executed by the distribution licensee unless mutually agreed otherwise by the distribution licensee with the applicant, on mutually agreed terms and conditions.

Note: The provisions under the first proviso to this regulation shall also apply for execution of service lines to be executed exclusively for a group of applicants or consumers, as the case may be, if all the members of such group enter into an agreement amongst themselves and nominate their representative who shall then deal with the distribution licensee for such matters.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity ) Regulations, 2012
Section17
Marginal noteExecution of works
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Suppl… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.