Section 14: Penalty or Compensation

The Himachal Pradesh Electricity Regulatory Commission (Rooftop Solar PV Grid Interactive Systems based on Net Metering) Regulations, 2015State Regulations of Himachal Pradesh · 2003

In case of failure of net metering system, the provisions of penalty or compensation shall be applicable as per the provisions of the Himachal Pradesh Electricity Regulatory Commission (Distribution Performance Standards) Regulations, 2010.

1 Added words for sub-regulation (10) vide Not. No. HPERC-H(1)-11/2015dated 6th November, 2018 published in R.H.P. dated 14th November, 2018 at p. 6010-6016.

14 Compendium of HPERC Regulations, March 2021

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Rooftop Solar PV Grid Interactive Systems based on Net Metering) Regulations, 2015
Section14
Marginal notePenalty or Compensation
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Rooftop Solar PV Grid Interactive… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.