On receipt of the No Objection Certificate, the applicant shall submit an application for approval of the plan of the building to be constructed on the approved site to the Licensing Authority. Such application shall be accompanied by,-

(i) a copy of the no objection certificate granted under rule 27;

(ii) a copy of the approved site plan;

(iii) complete plan, elevation and sections in quadruplicate in original printed on tracing film and also in digital format with four prints of the premises and of all erections and buildings thereon drawn correctly to a scale of not less than 1:100 on prints taken out of any of the standard size tracings and showing clearly,-

(a) all dimensions in millimeters and materials of construction indicating the different materials in distinguishing colours and giving in figures dimensions the width and depth of walls, beams, scantlings and trusses;

(b) the width of all staircases and the number of steps in each flight with the rise and tread of steps the clear width of corridors, passages, openings, aisles and gangways as well as the height and constructions of all galleries, tiers, balconies and stages; and fire resistance rate of staircases shall be one hour. No gas pipeline or electrical lines shall be attached to it. Anti slippery nosing shall be installed for the steps. One metre height of handrail be provided.

(c) the sizes of all doors, windows and ventilators indicating their construction and the way in which they open and the proposed system of ventilation;

(d) the proposed seating arrangement;

(e) the plinth area of each building in square meters separately for ground floor and upper floors and in tiers, galleries or balconies;

(f) staircases;

(g) water closets and urinals;

(h) levels at the different parts of the building in plans and sections; and

(i) details and positions of projectors, screen, sound box and other plants and equipment;

(iv) detailed specifications of the works in triplicate to be executed, sufficiently describing the material to be employed and the mode of construction to be adopted with calculations, in triplicate showing the loads coming and stresses occurring in all foundations, piers, columns, stanchions, lintels, beams, slabs, joists and trusses, such calculations being certified to be correct by a graduate engineer or a design engineer or a design practitioner or a qualified architect

31. Procedure for approval of plans, etc._ (1) On receipt of the application and particulars specified in rule 30, the Licensing Authority shall simultaneously forward the applications and particulars to the Town Planning Officer of City Corporation / Urban Development Authority/ Planning Authority / Assistant Director Town and Country Planning as to verify whether the building plans satisfy the requirements of these rules and whether the building proposed to be built is suitable for a cinema and to submit a report to the Licensing Authority within fifteen days.

(2) On receipt of the report under sub-rule (1), the Licensing Authority shall forward the connected records to the executive engineer, Public works Department of the district. The executive engineer, Public works, Ports and inland transport Department shall examine the design calculations and if he is satisfied after scrutiny that the building if constructed as per the specifications and designs would be sound enough, he shall within fifteen days forward his report to the Licensing Authority, attaching a certificate that the specifications and designs are acceptable.

(3) On receipt of the acceptance of design and specification by the executive engineer Public works, Ports and inland transport Department, the Licensing Authority shall direct the applicant to submit the plan, elevation and electrical drawings in quadruplicate in blue print or computer print and also in digital format showing the location of the cinematograph apparatus and complete electrical installations wiring diagram indicating all wiring, light- points, switches, plugs, distribution boards and other electric machinery indicating different circuits in different colours and earthing details to the Electrical Inspector.

(4) Thereafter, the Electrical Inspector shall examine the designs pertaining to the cinematograph plant, the electrical installations along with electrical wiring diagram and plan details showing the electrical system submitted by the applicant and if he is satisfied after scrutiny, that they are in accordance with the provisions of these rules relating to safety of electrical installation, he shall forward his report to the Licensing Authority within fifteen days.

Where this provision sits

ActThe Karnataka Cinemas (Regulation) Rules, 2014.
Section30
Marginal noteApplication for approval
JurisdictionState of Karnataka
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Karnataka Cinemas (Regulation) Rules, 2014. is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.