(1) The Sanctioning Authority shall verify and may issue or refuse the permit, not later than Thirty days from the date of receipt of application along with the plans and documents as under regulation 4. In case of refusal, the reasons for the same shall be clearly mentioned. Public objections, received if any during this period shall be reviewed and disposed by the Sanctioning Authority.
(2) The permit issued shall be a work permit and the construction or erection of telecommunication tower or telecommunication pole structures or accessory rooms essential for the use of such tower or pole structures shall be completed within two years from the date of issue of such permit.
(3) The period of the permit shall be extended for a further period of two year if an application for the same is submitted to the Sanctioning Authority, within the valid period of the permit duly paying 25% of the prescribed fee and charges and in the prescribed form duly attaching the original permit in these regulations.
6(A). All existing telecom towers shall register within 03 months from the date of publication of this notification in official gazette failing which the concerned local body shall initiate action for demolition as per the Act provisions duly following the procedures.