(1) All works executed by the Municipality shall be measured at least once in a month or at such periodicity agreed upon in the contract and recorded in the Measurement Book. On recording in the Measurement Book a bill shall be raised.
Provided that, in the case of small works, the execution of which runs over only a few days, works may be measured up and paid once for all after their completion, and the agreements with the contractors shall provide for this wherever applicable.
(2) Check measurements of works shall ordinarily be made as early as possible after recording the measurements in the Measurement Book. In no case, check measurements shall be 51 delayed for more than a period of two weeks from the date of completion of the work.