( 1) Where tests of any materials are made to ensure conformity with the· requirements of these rules, records of the test data shall be kept available for inspection during the construction of the building and for·such period thereafter as required by the Agency. •
(2) The person to whom permission is issued shall during construction keep:- . (a) posted in conspicuous place on the property in respect of which the permission was issued, a copy of the permission for building and or development, as the case may be; and.
(b) a copy of the·· approved drawing-S and specifications referred to in rule 22 of the property in respect of which the permission was issued. •
37. Inspection by the Agencies- ( 1) Generally every construction or work for which permission is required or issued shall be subject to inspe~tion by the Agency. The Agency may appoint · special inspectors, if the construction involves hazards or require constant inspection.
(2) Inspection, where required, shall be made within 7 days following the receipt of notice regarding start of work on the site. After the expiry of such period the applicant or owner shall be free to continue the construction according to the sanctioned plan. At the first inspection, -the Agency shall determine to the best of its • ability, whether the building has been located in accordance with the approved plans. The final inspection of the completed work shall be made within 21 days following the • receipt of notice • regarding completion of work at site.
-i::r~ ~. ~ 14 llfi=f 2016 222 (197)
(3) When inspe.ction of any construction operation reveals any Jack of safety precaution, the • Agency shall have right .. to direct the applicant or owner to stop the work immediately until the necessary remedial measures are taken.