(i) The capacities not assigned to any of the Discoms
(ii) Additional capacities, if any, added from the new generating stations expected during FY 2013-14
(iii) Un-allocated energy to the Discoms, out of the available energy, in the Tariff Order for FY 2013-14 due to 'Merit Order Dispatch (MOD)'.
Subject to the condition that three distribution companies of the State shall be having first charge on such capacities. MP PMCL will allocate power as per the requirement subject to the available capacity and surplus power if any, shall be traded by MP PMCL. Bulk Power Supply Tariff shall be decided by the Appropriate Commission.
Table - 4: Generating Stations Allocated to MP PMCL New Generation Stations NTPC Sipat - Stage I (3 units) NTPC Korba - III IPP Torrent Singaji TPS Phase 1 Unit-l Singaji TPS Phase 1 Unit-2 Satpura TPS Extension Unit-1O Satpura TPS Extension Unit-II NTPC Mauda TPS Unit-l NTPC Mauda TPS Unit-2 Vindhyachal Mega Project Stage 4, Unit 1 Vindhyachal Mega Project Stage 4, Unit 2 DVC Durgapur Steel TPS Unit-l DVC Durgapur Steel TPS Unit-2 UMPP Sasan, Sidhi Bina Power, Sagar Unit-l Bina Power, ~agar Unit-2 Jaiprakash Power, Nigri, Unit-l Jaiprakash Power, Nigri, Unit-2 MB Power, Annupur BLA Power, Narsinghpur Mis Jhabua Power, Seoni Lanco TPS, Amarkantak Installed Capacity (MW) 1980 500 1147 600 600 250 250 500 500 500 500 500 500 1320 250 250 660 660 600 45 600 300 % 17% 100% 100% 100% 100% 16% 16% 26% 26% 10% 10% 38% 70% 70% 38% 37% 35% 35% 35% 100% MP Share MW 341 77 100 600 600 250 250 78 78 143 128 50 50 495 175 175 248 247 210 16 210 300 Total ..13,012.00 4,821.00 In addition to above additional capacity, if any including Central! State Sector the same shall also be assigned to MP PMCL.
230 (2) 11~ ~, fu:ficf; 19 11fCf 2013