(1) Every market committee shall entrust to the Board all the civil work including electrical work other than original work, the cost of which does not exceed Rs.3,000 (Rupees three thousand only) and the maintenance and repair work the cost of which does not Exceed Rs.50,000 (Rupees fifty Thousand only)
(2)Where the market committee entrusts any work to Board under sub-rule
(1), the market committee shall pay to the Board 50 percent of the estimated cost of work as soon as the contract is settled as first instalment. On receipt of certificate of utilization of the amount of the first instalment, 25 percent of the total estimate cost shall be paid as second instalment and the balance amount shall be paid on receipt of certificate of utilization of the amount of second instalment.
(3) The Board shall commence the work immediately on receipt of amount of first instalment.