(1) As soon as may be, but not later than three months from the date of receipt of the New Town Development Programme from the New Town Development Authority under rule 10, the Government shall either approve the New Town Development Plan or shall approve it with such modifications as they may consider necessary or may return the New Town Developemnt Plan to the New Town Development Authority to modify the plan or to prepare a fresh plan as directed.
Amended vide G.O.Ms.No.454 dt. 6.4.88
(2) If the Government has ordered any material modification in the New Town Development Plan, the New Town Development Authority shall carry out such modifications and resubmit the plan within three months or within such time as the Government may permit.
(3) In case, the Government have ordered the preparation of a fresh plan, the New Town Development Authority shall prepare a fresh plan in accordance with such directions as may be given in this behalf and submit to Government after following the procedure and time limit prescribed under these rules.