Section 23: Sanction of plan in case of delays

Tripura Building Rules — 2017State Rules of Tripura · 1994

If within the period specified in these rules, the Local Body has neither sanctioned nor refused to accord sanction to execute any work, the applicant may represent to the Mayor/Chairperson in writing, in this regard and if the representation is not disposed of within 30(thirty) days from the date of receipt of the representation, such sanction or permission shall be deemed to have been granted and the applicant may proceed to execute the work. 80, however that nothing in the sanction shall be deemed to have permitted the applicant to contravene any of the provisions of this rule or any other rules or regulations applicable to such works.

Where this provision sits

ActTripura Building Rules — 2017
Section23
Marginal noteSanction of plan in case of delays
JurisdictionState of Tripura
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? Tripura Building Rules — 2017 is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.