(1) A sanction to erect a building accorded under these rules shall be valid for 3(three) years from the date on which it is sanctioned and may be renewed thereafter for a further period of 2(two) years on payment, in the form of cash or bank draft, of such fees as may be determined by the Local Body on the basis of rule 25, and on production of the previously sanctioned plan. A building plan may be revalidated for a further period of 5 years only in case a building has been partly completed and occupancy certificate in terms of rule 34 has been issued as well as on production of the previous sanctioned/revalidated building plan, the completion certificate and on receipt of fees required to be paid as to be determined by the ULB from time to time;
provided that, if the application for renewal of a building is made after the expiry of 3(three) years, the same shall be accompanied by a renewal fee with a fine not being less than Rupees 2(two) thousand or as may be determined by the ULB concerned.
(2) Any person who erects a building or continues the work of erection of a building after the permission sanctioned under these rules has expired, shall be deemed to erect such building or to continue such work without sanction;
(3) The erection of a building or work shall be completed within the period specified by the Local Body under section 211 of the Act.