CourtMesh

Section 24: Procedure for shifting electric line or electrical plant of the Licensee

Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017Union territory Regulations of Delhi · 2003

(1) The owner of the land or his successor in interest, who has given right of way for the construction of an existing electric line or electrical plant over, under, along, across, in or upon the said land, may apply for shifting the electric line or electrical plant to any other portion of his land for genuine purposes:

(2) The application for shifting the electric line or electrical plant shall be submitted to the Licensee.

(3) On receipt of the application, the Licensee shall inspect the site and assess the technical feasibility of the proposed shifting.

(4) The request for shifting an electric line or electrical plant shall be granted only if:-

(i) the proposed shifting is technically feasible. and

(ii) the owner of the land or his successor in interest gives consent in writing to shift the electric line or electrical plant to any other portion of his land or to any other land owned by him or any alternate right of way to be arranged by him for shifting the electric line and the electrical plant and

(iii) the owner of the land or his successor in interest shall take necessary permission/approval for road cutting or right of way, if required.

(iv) the applicant remits the applicable charges required for shifting the electric line or electrical plant.

(5) The Licensee shall shift the electric line or electrical plant, if the conditions specified in sub-regulation (4) are complied with by the applicant.

(6) In case of shifting of meter or service line within the premises of the consumer, the procedure specified in the Regulation 25 shall apply.

Where this provision sits

ActDelhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulations, 2017
Section24
Marginal noteProcedure for shifting electric line or electrical plant of the Licensee
JurisdictionUnion territory of Delhi
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? Delhi Electricity Regulatory Commission (Supply Code and Performance Standards) Regulatio… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.