(1) The consumer shall apply to the Licensee for shifting the meter within the existing premises or for deviation of existing service line within his property.
(2) The Licensee shall conduct the site inspection.
(3) The charges for shifting of meter and service line for the connection on the same premises shall be as notified in the Commission’s Orders.
(4) If shifting requires new service line, the Licensee shall be entitled to levy the Service Line cum Development charges.
(5) The following time schedule shall be observed for completing the works from the date of payment of expenditure:- Sl. No. Purpose Time Schedule
(i) shifting of meter 7 (seven) days
(ii) shifting of LT service line 30 (thirty) days
(iii) shifting of HT service line 45 (forty five) days [PART III DELHI GAZETTE : EXTRAORDINARY 81
Provided that the above timelines for shifting of LT & HT lines shall be computed after deducting the time taken for obtaining statutory clearances/permission such as road cutting permission, if any.
26. Additional Charges:
The charges for installation, inspection, special meter reading, reconnection etc. shall be charged by the Licensee as notified in the Commission’s Orders.
CHAPTER - V METERING, BILLING AND PAYMENT Metering