Section 14: Execution of Long-term Access Agreement

The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Relate…State Regulations of Himachal Pradesh · 2003

The applicant shall sign an agreement for long-term access with the State Transmission Utility/distribution licensee in case longterm access is granted in accordance with the provisions as may be made in the detailed procedure. While seeking long-term access to an intra-State transmission licensee(s), other than the State Transmission Utility, the applicant shall sign a multi party long-term access agreement with the State Transmission Utility and the intra-State transmission licensee(s).

The long–term access agreement shall contain the date of commencement of long-term access, the payment security mechanism for the term of long-term open access in accordance with the detailed procedure, the point of injection of power into the grid and point of drawl from the grid and the details of dedicated transmission/ distribution lines, if any, required. In case augmentation of transmission/ distribution system is required, the long-term access agreement shall contain the time line for construction of the facilities of the applicant and the transmission/ distribution licensee, the bank guarantee required to be given by the applicant and other details in accordance with the detailed procedure.

Where this provision sits

ActThe Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium-term Intra-State Open Access and Related Matters) Regulations, 2010
Section14
Marginal noteExecution of Long-term Access Agreement
JurisdictionState of Himachal Pradesh
StatusIn force as published by the source

Find the provision, not just read it

The full text above is free, and it stays free. What a free CourtMesh account adds is everything you cannot do by reading one page at a time:

  • Search 49,000+ Central and State enactments by what a provision says, not by its number
  • Jump from any section to every judgment that has applied it
  • Search 300 million+ Indian court records alongside the statute
  • Ask a research agent to find and read the case law on a provision for you

Free account. No card. About a minute to create.

Create a free account

Need this as data, not as a page? The Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term… is one of 49,000+ enactments on CourtMesh. The Indian court cases API serves the case law that cites these provisions over JSON, with API documentation and plans and pricing. See also the judgment library.