Demand notice valid for 90 days shall be sent by the registered AD post to the applicant within the time frame laid down in Himachal Pradesh Electricity Regulatory Commission (Licensee’s Duty for supply of Electricity on Request) Regulations, 2004:
Provided that the demand notices to be issued on or after the date of commencement of these regulations shall suitably incorporate the terms and conditions of these regulations, apart from other conditions as per other Regulations and Codes of the Commission:
Provided further that if any of the terms and conditions of these regulations remain unaccounted for in any of the demand notices issued on or within 90 days from the date on which these regulations come into force, the licensee may revise the same, so as to incorporate the terms and conditions as per these Regulations and the Act:
Provided further that the demand notices issued prior to commencement of these Regulations and/or the demands still to be raised against the loads/demands released prior 18 Compendium of HPERC Regulations, March 2020 to commencement of these Regulations, shall continue to be governed by the Himachal Pradesh Electricity Regulatory Commission (Recovery of Expenditure for Supply of Electricity) Regulations, 2005 and other relevant Regulations and Codes of the Commission, but not including these Regulations, unless the Commission issues any specific order in this regard:
Provided further that in case of non-compliance of the demand notice within the period mentioned in such notice or within such period as may be mutually agreed between the licensee and the applicant, the application, against which the demand notice had been issued, shall be treated as withdrawn and the matter shall be further dealt with in accordance with relevant governing Regulations and Codes of the Commission.